Guidestone Financial Resources

Exterior Envelope Restoration Services

Project Overview

Due to normal environmental wear and tear of the existing roofing systems, GuideStone began experiencing failures and leaks that were more intensive than routine maintenance could handle. ECI was contracted to evaluate the exterior Roof Areas and 3rd Floor Terrace Deck conditions of their headquarters located in Dallas, Texas. Once the thorough evaluation of all roofing system components on the seven-story office building was performed, ECI determined that the original construction materials had exceeded their serviceable life cycles and were in need of full replacement. ECI provided our professional services on every aspect of the construction process.

Consulting Services Provided

Evaluation: Performed extensive evaluation of roofing and terrace deck waterproofing systems to determine extent and severity of system distress. Provided summary report of existing exterior conditions with a detailed program for system replacement and repairs, which included plans, photographs, construction budget and schedule.

Construction Documents: Designed exterior roof system replacement and repairs, which included specifications, bid documents, construction drawings, and details for all associated facility repairs.

Construction Administration: Administered all aspects of the construction project including: conducted pre-bid meeting, reviewed contractor submittals and pay application requests, conducted progress meetings, reviewed change orders for cost control, and approved all final close out documents.

Quality Assurance: Performed part time quality assurance site audits of work in progress including: photographs, documentation and written reports of findings and recommendations.

Before and After Photographs

2.JPG
1.JPG
3.JPG
4.JPG
5.JPG
6.JPG
7.JPG
8.JPG
9.JPG
10.JPG
11.JPG
13.JPG
12.JPG
14.JPG
15.JPG
17.JPG
16.JPG
19.JPG
18.JPG
21.JPG
20.JPG
22.JPG